Project : ID036 Introduction of 2.1MW Rooftop Solar Power System in Woodworking Factories

Project title Introduction of 2.1MW Rooftop Solar Power System in Woodworking Factories
Ref No. ID036
PDD form
Monitoring plan
Name of project participants (Indonesia) PT. AST Indonesia
Name of project participants (Japan) Sumitomo Forestry Co., LTD.
Name of third party entity (TPE) TPE-ID-011 PT. MUTUAGUNG LESTARI
Location of project Country: Republic of Indonesia
Region/State/Province etc: Central Java province
City/Town/Community etc: Semarang City
Latitude, longitude:

6°58'14"S and 110°19'47"E

Duration Starting date of project operation: 01 Mar 24
Expected operational lifetime of project: 11 years
Methodology No.
Emission Reductions (tCO2e) Estimated emission reductions in each year
  • - (in 2013)
  • - (in 2014)
  • - (in 2015)
  • - (in 2016)
  • - (in 2017)
  • - (in 2018)
  • - (in 2019)
  • - (in 2020)
  • - (in 2021)
  • - (in 2022)
  • - (in 2023)
  • 1,365 (in 2024)
  • 1,565 (in 2025)
  • 1,565 (in 2026)
  • 1,565 (in 2027)
  • 1,565 (in 2028)
  • 1,565 (in 2029)
  • 1,565 (in 2030)
Status Validation
Public comments
  • 23 Jan 25  -  21 Feb 25