Project title |
Small Scale Solar Power Plants for Schools in Island States Ref No. PW002 PDD form Monitoring plan Supporting documentation |
---|---|
MoC(PDF) |
MoC |
Name of project participants (Palau) | Palau Adventist Schools |
Name of project participants (Japan) | Pacific Consultants Co., Ltd. (PCKK) |
Name of third party entity (TPE) | TPE-PW-002 Japan Management Association |
Location of project |
Country: Republic of Palau Region/State/Province etc: Site A: Koror State; Site B: Airai State City/Town/Community etc: Site A: Madalaii Hamlet; Site B: Ngerikiil Hamlet Latitude, longitude: Site A: N 7°20'29" and E 134°28'36"; Site B: N 7°22'31" and E 134°33'28" |
Duration |
Starting date of project operation: 08 Feb 16 Expected operational lifetime of project: 20 years |
Methodology No. | |
Emission Reductions (tCO2e) |
Estimated emission reductions in each year
|
Status | Project registered |
Public inputs |
|
Registration |
|
Monitoring period | 08 Feb 16 - 31 Jul 17 |
---|---|
Monitoring report(PDF) | Monitoring report(PDF) |
Issuance request state |
Verification report
Issued
(Palau)
-Notified amount of credits to be issued: 37
-Issued amount of credits and serial number: 37, JCM-PW-002-01-01-PW-0000075 - JCM-PW-002-01-01-PW-0000111
-Date of Issuance: 08 Feb 18
(Japan)
-Notified amount of credits to be issued: 108
-Issued amount of credits and serial number: 108, JCM-PW-JP-223-330-00201
-Date of Issuance: 30 Jan 18
|