The Joint Committee adopted the decisions on documents, proposed JCM methodology, and third party entities.
Adopted documents:
Rules of Implementation for the Joint Crediting Mechanism (JCM) (version 02.0)
JCM Project Cycle Procedure (version 02.0)
JCM Verification Report Form (version 02.0)
JCM Credits Issuance Request Form (version 02.0)
JCM Guidelines for Developing Project Design Document and Monitoring Report (version 02.0)
JCM Guidelines for Designation as a Third-Party Entity (version 02.0)
Common Specifications of the JCM Registry
Approval of proposed methodologies with revisions:
SA_AM001 "Introduction of High Efficiency Electrolyzer in Chlor-Alkali Processing Plant"
Designation of third-party entities:
– Japan Quality Assurance Organization (JQA)
– Lloyd’s Register Quality Assurance Limited (LRQA)