| Project title |
Small scale solar power plants for commercial facilities in island states Ref No. PW001 PDD form Monitoring plan Supporting documentation |
|---|---|
| MoC(PDF) |
MoC |
| Name of project participants (Palau) | Subproject 1: Western Caroline Trading Company, Subproject 2: Surangel and Sons Company |
| Name of project participants (Japan) | Pacific Consultants Co., Ltd. (PCKK) |
| Name of third party entity (TPE) | TPE-PW-002 Japan Management Association |
| Location of project |
Country: Republic of Palau Region/State/Province etc: Koror State City/Town/Community etc: N/A Latitude, longitude: Subproject 1: N 7° 21’ 01.9” and E 134° 28’ 48.4” Subproject 2: N 7° 20’ 30.6” and E 134° 28’ 41.9” |
| Duration |
Starting date of project operation: 23 Oct 14 Expected operational lifetime of project: Subproject 1: 20 years, Subproject 2: 20 years |
| Methodology No. | |
| Emission Reductions (tCO2e) |
Estimated emission reductions in each year
|
| Status | Project registered |
| Public inputs |
|
| Registration |
|
| Monitoring period | 01 Dec 15 - 31 Dec 20 |
|---|---|
| Monitoring report(PDF) | Monitoring report(PDF) |
| Issuance request state |
Verification report
(Palau)
-Notified amount of credits to be issued:
-Issued amount of credits and serial number:
-Date of Issuance:
(Japan)
-Notified amount of credits to be issued:
-Issued amount of credits and serial number:
-Date of Issuance:
|
| Monitoring period | 23 Oct 14 - 30 Nov 15 |
|---|---|
| Monitoring report(PDF) | Monitoring report(PDF) |
| Issuance request state |
Verification report
Issued
(Palau)
-Notified amount of credits to be issued: 74
-Issued amount of credits and serial number: 74, JCM-PW-001-01-01-PW-0000001 - JCM-PW-001-01-01-PW-0000074
-Date of Issuance: 22 Dec 16
(Japan)
-Notified amount of credits to be issued: 222
-Issued amount of credits and serial number: 222, JCM-PW-JP-1-222-00101
-Date of Issuance: 22 Dec 16
|